BRIDGE TEMPORARY WORKS RESEARCH PROGRAM

Author(s)
DUWADI, SR
Abstract

The collapse of falsework on the route 198 overpass on the baltimore-washington parkway was determined to be caused by shoring towerfailures, and led to the federal highway administration recommending the revision of specifications and guidelines relating to falsework. This article reviews several recent falsework failures, and describes a multidisciplinary falsework research task force. The priorityactivities of the task force are as follows: survey specifications on bridge temporary works; establish standard specifications; develop a design manual; develop recommendations related to certification program on suppliers' products; and develop a construction manual. The end products of the fhwa program will be a synthesis of all codesand specifications dealing with the subject, a standard specification, and a design manual.

Request publication

9 + 1 =
Solve this simple math problem and enter the result. E.g. for 1+3, enter 4.

Publication

Library number
I 848118 IRRD 9206
Source

PUBLIC ROADS WASHINGTON D.C. USA 0033-3735 SERIAL 1991-09-01 E55 2 PAG: 37-40 T5

Our collection

This publication is one of our other publications, and part of our extensive collection of road safety literature, that also includes the SWOV publications.