Behaviour during construction of a stabilised base embedded wall at Coventry. Prepared for the Highways Agency, Quality Services (Civil Engineering).

Auteur(s)
Hayward, T. Carder, D.R. Powrie, W. & Richards, D.J.
Jaar
Samenvatting

Instrumentation has been installed to monitor the behaviour of a bored pile retaining wall with a stabilising base during and after its construction of the Coventry North-South Road scheme in Warwickshire. Wall movements, wall and base bending moments, loads in the temporary props, and vertical pressures beneath the permanent stabilising base were monitored. In this report, the ground conditions, construction sequence and instrumentation are described and the field measurements during construction and its first two years in service are discussed. The results are compared with a finite element back-analysis and outline recommendations made for the design of similar structures in the future. (A)

Publicatie

Bibliotheeknummer
C 15112 [electronic version only] /53 / IRRD E105782
Uitgave

Crowthorne, Berkshire, Transport Research Laboratory TRL, 2000, IV + 26 p., 14 ref.; TRL Report ; No. 446 - ISSN 0968-4107

Onze collectie

Deze publicatie behoort tot de overige publicaties die we naast de SWOV-publicaties in onze collectie hebben.