Dynamic barrier used to solve a large construction dewatering problem.

Auteur(s)
Holley, C.E. Ross, J.E. & Ghadiali, B.M.
Jaar
Samenvatting

This paper outlines the description of a dynamic barrier installed between a railroad trench under construction and an existing toxic plume floating on the surface of ground water adjacent to an oil recycling facility. The Alameda Corridor Transportation Authority (ACTA), in April, 2002 completed construction of a 32km railroad transportation project which ranks as one of the largest freight transportation projects ever undertaken and one of national significance. The project includes 16km of surface tracks and a 16km below-surface Trench section along Alameda Street. The Trench portion will carry two railroad tracks beneath existing streets. During Trench construction, significant quantities of toxic waste were encountered in soil and groundwater from adjacent facilities. This paper describes one such encounter and the solution chosen to avoid costly construction delays while providing for environmental safeguards. For the covering abstract see ITRD E120462.

Publicatie aanvragen

10 + 2 =
Los deze eenvoudige rekenoefening op en voer het resultaat in. Bijvoorbeeld: voor 1+3, voer 4 in.

Publicatie

Bibliotheeknummer
C 28732 (In: C 28674) /15 /54 /51 / ITRD E120520
Uitgave

In: Urban transport IX : urban transport and the environment in the 21st century : proceedings of the Ninth International Conference on Urban Transport and the Environment in the 21st Century, Crete, Greece, 10 - 12 March 2003, p. 589-597, 2 ref.

Onze collectie

Deze publicatie behoort tot de overige publicaties die we naast de SWOV-publicaties in onze collectie hebben.