Use of the full closure method on I-84 was an innovative idea that was deemed to be a success. With the availability of many alternate routes, signal timing changes on the alternate routes, a large-scale public outreach effort, and the communication between agencies, ODOT’s use of full closure on I-84 resulted in timely completion of the project with increased quality and reduced risk for workers and motorists. For transportation professionals who must rehabilitate roadways and reduce the impacts of work zones on workers and motorists, full road closure is one potential method that can achieve both goals. With adequate planning, public outreach, stakeholder involvement, and alternate routes, full road closure has the potential to simultaneously accelerate projects, improve quality and safety, and reduce costs. (Author/publisher)