The study described here expands the National Bus Company costing system to estimate the marginal cost of adding either peak-only or all-day buses. Peak costs are compared with off-peak costs for different definitions of the peak, and for different allocations of overheads. In all cases, off-peak patronage is shown to be subsidizing peak operation, and considerations involved in differential pricing are discussed.

Publicatie

Bibliotheeknummer
B 10594 (In: B 10591 S) /10/72/
Uitgave

In: Symposium on the costing of bus operations, Crowthorne, June 26 and 27, 1975, p. 14-30, 12 graph., 8 tab., 3 ref.