Traffic delays due to resurfacing of M4 motorway 1970.

Auteur(s)
MacLean, A.D.
Jaar
Samenvatting

Measurements carried out during the resurfacing of the M4 motorway, to enable estimates to be made of the delays caused to traffic by these road-works, and the cost to the community of these delays are described. The total number of vehicle-hours lost was estimated to be 13700 representing a cost to the community of 10500.

Publicatie

Bibliotheeknummer
A 9454 [electronic version only] IRRD 55607
Uitgave

Crowthorne, Road Research Laboratory RRL, 1971, 13 p. tekn. tab.; RRL Report 421.